Question : A, B, and C can separately do work in 6, 10, and 15 days respectively. They started to work together but C left after 2 days. In how many days will the remaining work be finished?
Option 1: $1 \frac{2}{4}$
Option 2: $1 \frac{1}{4}$
Option 3: $1 \frac{5}{8}$
Option 4: $2 \frac{7}{4}$
Latest: SSC CGL preparation tips to crack the exam
Don't Miss: SSC CGL complete guide
New: Unlock 10% OFF on PTE Academic. Use Code: 'C360SPL10'
Correct Answer: $1 \frac{1}{4}$
Solution : Given, A, B, and C can separately do a work in 6, 10, and 15 days, respectively. Work done by A in a day= $\frac{1}{6}$ Work done by B in a day = $\frac{1}{10}$ Work done by C in a day = $\frac{1}{15}$ Work done by A, B, and C together in a day = $\frac{1}{6}+\frac{1}{10}+\frac{1}{15}$ = $\frac{1}{3}$ Work done by A, B, and C together in 2 days = $\frac{2}{3}$ Work left for A and B to do = $1-\frac{2}{3}=\frac{1}{3}$ Work done by A and B together in 1 day = $\frac{1}{6}+\frac{1}{10}=\frac{4}{15}$ $\therefore$ Time taken by them to complete the work = $\frac{\frac{1}{3}}{\frac{4}{15}}$ = $\frac{5}{4}$ days Hence, the correct answer is $1\frac{1}{4}$ days.
Candidates can download this ebook to know all about SSC CGL.
Answer Key | Eligibility | Application | Selection Process | Preparation Tips | Result | Admit Card
Question : A and B can do a piece of work in 5 days and 10 days, respectively. They began the work together but A left after some days and B finished the remaining work in 8 days. After how many days did A leave?
Question : A, B, and C can separately complete a work in 12, 15, and 20 days, respectively. They worked together for 4 days. What will be the remaining work?
Question : A, B and C can work separately in 18, 36 and 54 days. They started the work together, but B and C left 5 days and 10 days, respectively, before the completion of the work. In how many days was the work finished?
Question : P, Q, and R can complete a piece of work in 10 days, 15 days, and 20 days, respectively. If they work together, in how many days can they finish the same work?
Question : A, B, and C can do a job in 6 days, 12 days and 15 days respectively. After $\frac{1}{8}$th of the work is completed, C leaves the job. The rest of the work is done by A and B together. The time taken to finish the work is:
Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile