Question : A can do a certain work in 9 days. B is 80% more efficient than A. How many days will B and A together take to do the same work?

Option 1: $\frac{45}{14}$ Days

Option 2: $\frac{54}{13}$ Days

Option 3: $\frac{47}{14}$ Days

Option 4: $\frac{44}{13}$ Days


Team Careers360 8th Jan, 2024
Answer (1)
Team Careers360 10th Jan, 2024

Correct Answer: $\frac{45}{14}$ Days


Solution : According to the question,
A can do a certain work in 9 days.
B is 80% more efficient than A.
So, the ratio of efficiencies of A and B = 100 : 180 = 5 : 9
Total work = Time $\times$ Efficiency
⇒ Total work = 9 $\times$ 5 = 45 units
Consider the total efficiency of A and B = 5 + 9 = 14
Total work completed by A and B together = $\frac{45}{14}$ days.
Hence, the correct answer is $\frac{45}{14}$ Days.

How to crack SSC CHSL

Candidates can download this e-book to give a boost to thier preparation.

Download Now

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books