Question : A can do $\frac{1}{3}$ of a work in 30 days. B can do $\frac{2}{5}$ of the same work in 24 days. They worked together for 20 days. C completed the remaining work in 8 days. Working together A, B and C will complete the same work in:
Option 1: 15 days
Option 2: 10 days
Option 3: 18 days
Option 4: 12 days
Latest: SSC CGL preparation tips to crack the exam
Don't Miss: SSC CGL complete guide
New: Unlock 10% OFF on PTE Academic. Use Code: 'C360SPL10'
Correct Answer: 12 days
Solution : A can do $\frac{1}{3}$ of a work in 30 days. So, A can finish the complete work in 90 days if working alone. ⇒ 1 day work of A = $\frac{1}{90}$ B can do $\frac{2}{5}$ of a work in 24 days. So, A can finish the complete work in 60 days if working alone. ⇒ 1 day work of B = $\frac{1}{60}$ So, 1 day work of both A and B = $\frac{1}{90}$ + $\frac{1}{60}$ = $\frac{1}{36}$ Work done by A and B together in 20 days = 20 × $\frac{1}{36}$ = $\frac{20}{36}$ Remaining work = 1 – $\frac{20}{36}$ = $\frac{4}{9}$ This work is done by C in 8 days. So, 1-day work of C = $\frac{\frac{4}{9}}{8}$ = $\frac{1}{18}$ 1 day work of (A + B + C) = $\frac{1}{36}$ + $\frac{1}{18}$ = $\frac{1}{12}$ So, the time taken by (A + B + C) = $\frac{1}{\text{1 day work of A, B, and C}}$ = $\frac{1}{\frac{1}{12}}$ = 12 days Hence, the correct answer is 12 days.
Candidates can download this ebook to know all about SSC CGL.
Answer Key | Eligibility | Application | Selection Process | Preparation Tips | Result | Admit Card
Question : A can do $\frac{1}{3}$rd of a piece of work in 32 days, B can do $37 \frac{1}{2}$% of the same work in 24 days, while C can do 60% of the same work in 48 days. B and C together started and worked for x days. After x days, B left and A joined C and together, completed the
Question : A and B together can do a piece of work in 36 days and B and C together can do it in 24 days. A and C together can do it in 18 days. The three working together can finish the work in:
Question : A, B, and C can separately complete a work in 12, 15, and 20 days, respectively. They worked together for 4 days. What will be the remaining work?
Question : A and B can do a piece of work in 5 days and 10 days, respectively. They began the work together but A left after some days and B finished the remaining work in 8 days. After how many days did A leave?
Question : A, B, and C can separately do work in 6, 10, and 15 days respectively. They started to work together but C left after 2 days. In how many days will the remaining work be finished?
Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile