Question : A can finish a work in 24 days and B in 30 days, individually. They work together for 11 days. The percentage of the work still to be finished will be:

Option 1: 18%

Option 2: 16%

Option 3: 17.5%

Option 4: 12.5%


Team Careers360 20th Jan, 2024
Answer (1)
Team Careers360 21st Jan, 2024

Correct Answer: 17.5%


Solution : Time taken by A alone to complete the work = 24 days
⇒ Part of work done by A alone in a day = $\frac{1}{24}$
Time taken by B alone to complete the work = 30 days
⇒ Part of work done by B alone in a day = $\frac{1}{30}$
Let the time taken by A and B together to complete the work = $x$
⇒ Part of work done by A and B in a day = $\frac{1}{x}$
⇒ $\frac{1}{24}$ + $\frac{1}{30}$ = $\frac{1}{x}$
⇒ $\frac{5+4}{120}$ = $\frac{1}{x}$
⇒ $x$ = $\frac{120}{9}$ = $\frac{40}{3}$ days
Now, part of the work done by A and B in 11 days = $\frac{11}{\frac{40}{3}}$ = $\frac{33}{40}$
⇒ Part of work left = $\frac{7}{40}$
⇒ Percentage of work left = $\frac{7}{40}×100$ = 17.5%
Hence, the correct answer is 17.5%.

How to crack SSC CHSL

Candidates can download this e-book to give a boost to thier preparation.

Download Now

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books