7 Views

Question : A can finish a work in 25 days, and B can do the same work in 15 days. B worked for 10 days and left the job. A alone can finish the remaining work in how many days?

Option 1: $7 \frac{1}{3}$ days

Option 2: $6 \frac{1}{3}$ days

Option 3: $8 \frac{1}{3}$ days

Option 4: $5 \frac{1}{3}$ days


Team Careers360 12th Jan, 2024
Answer (1)
Team Careers360 14th Jan, 2024

Correct Answer: $8 \frac{1}{3}$ days


Solution : Rate of A $= \frac{1}{25}$
Rate of B $=\frac{1}{15}$
Combined rate of A and B $=\frac{1}{25}+\frac{1}{15}$
According to the question,
B worked for 10 days.
The amount of work completed by B $ =10×\frac{1}{15}=\frac{2}{3}$​ of the total work
⇒ Remaining work $=1-\frac{2}{3}=\frac{1}{3}$
A alone can finish the remaining work at the rate of $\frac{1}{25}$​ of the total work per day.
$\therefore$ A will finish the remaining work in $\frac{\frac{1}{3}}{\frac{25}{3}}=\frac{25}{3}=8\frac{1}{3}$ days
Hence, the correct answer is $8\frac{1}{3}$ days.

How to crack SSC CHSL

Candidates can download this e-book to give a boost to thier preparation.

Download Now

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books