2 Views

Question : A completes 30% of a project in 30 days. He then calls in B and they together finish the remaining work in 20 days. How long would B alone take to do the whole work?

Option 1: 40 days

Option 2: 80 days

Option 3: 120 days

Option 4: 20 days


Team Careers360 16th Jan, 2024
Answer (1)
Team Careers360 21st Jan, 2024

Correct Answer: 40 days


Solution : Given: A completes 30% of a project in 30 days.
Let the total work be 100 units.
Since we know that, Total work = Efficiency × Time.
So, A's efficiency is $\frac{30}{30}$ = 1 unit each day.
After that, he calls B and the two of them complete the remaining work in 20 days.
So, the work left is 70 units.
Assuming that B's efficiency is $x$ units per day.
So, $\frac{70}{(1+x)}=20$
⇒ $20+20x = 70$
⇒ $20x = 50$
⇒ $x = 2.5$ units per day.
So, if B worked by himself, it would require $\frac{100}{2.5}=40$ days
Hence, the correct answer is 40 days.

SSC CGL Complete Guide

Candidates can download this ebook to know all about SSC CGL.

Download EBook

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
GRE ® Registrations 2024
Apply
Apply for GRE® Test now & save 10% with ApplyShop Gift Card | World's most used Admission Test for Graduate & Professional Schools
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books