Question : A contractor undertook to finish a work in 92 days and employed 110 men. After 48 days, he found that he had already done $\frac{3}{5}$ part of the work, the number of men he can withdraw so that the work may still be finished in time is:

Option 1: 45

Option 2: 40

Option 3: 35

Option 4: 30


Team Careers360 3rd Jan, 2024
Answer (1)
Team Careers360 17th Jan, 2024

Correct Answer: 30


Solution : Given:
A contractor undertook to finish a work in 92 days and employed 110 men. After 48 days, he found that he had already done $\frac{3}{5}$ part of the work.
We know,
$\frac{M_{1}\times D_{1}}{W_{1}}=\frac{M_{2}\times D_{2}}{W_{2}}$
Where $M_1$ and $M_2$ are men, $D_1$ and $D_2$ are days and $W_1$ and $W_2$ are work done.
Let $n$ number of men be withdrawn.
So, $\frac{110 \times 48}{\frac{3}{5}} = \frac{(110-n) \times 44}{\frac{2}{5}}$
$⇒ 110 × 16 = (110-n) × 22$
$⇒160 = (110-n) × 2$
$⇒80 = 110-n$
$⇒n = 110 - 80$
$\therefore n = 30$
Hence, the correct answer is 30.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books