Question : A is 20% more efficient than B. How much time will they working together take to complete a job which A alone could have done in 29 days?
Option 1: $\frac{145}{11}$ days
Option 2: $\frac{116}{11}$ days
Option 3: $\frac{203}{11}$ days
Option 4: $\frac{174}{11}$ days
Latest: SSC CGL preparation tips to crack the exam
Don't Miss: SSC CGL complete guide
Correct Answer: $\frac{174}{11}$ days
Solution :
According to the question,
The efficiency of A is 20% more than that of B
Let the efficiency of B be 100%
$\therefore$ The efficiency of A = 120% of the efficiency of B
⇒ Efficiency of A = $\frac{6}{5}$ of efficiency of B
⇒ $\frac{\text{Efficiency of A}}{\text{Efficiency of B}} = \frac{6}{5}$
Now, Total work = Efficiency of A $\times$ Time taken by A
$=6× 29 =174$
Now, Total efficiency = $5 + 6=11$
Time taken by (A + B) to complete the whole work =$\frac{\text{Total work}}{\text{Total efficiency}}$
$=\frac{174}{11}$ days
Hence, the correct answer is $\frac{174}{11}$ days.
Related Questions
Know More about
Staff Selection Commission Combined Grad ...
Answer Key | Eligibility | Application | Selection Process | Preparation Tips | Result | Admit Card
Get Updates BrochureYour Staff Selection Commission Combined Graduate Level Exam brochure has been successfully mailed to your registered email id “”.