Question : A is 20% more efficient than B. How much time will they working together take to complete a job which A alone could have done in 29 days?

Option 1: $\frac{145}{11}$ days

Option 2: $\frac{116}{11}$ days

Option 3: $\frac{203}{11}$ days

Option 4: $\frac{174}{11}$ days


Team Careers360 24th Jan, 2024
Answer (1)
Team Careers360 25th Jan, 2024

Correct Answer: $\frac{174}{11}$ days


Solution : According to the question,
The efficiency of A is 20% more than that of B
Let the efficiency of B be 100%
$\therefore$ The efficiency of A = 120% of the efficiency of B
⇒ Efficiency of A = $\frac{6}{5}$ of efficiency of B
⇒ $\frac{\text{Efficiency of A}}{\text{Efficiency of B}} = \frac{6}{5}$
Now, Total work = Efficiency of A $\times$ Time taken by A
$=6× 29 =174$
Now, Total efficiency = $5 + 6=11$
Time taken by (A + B) to complete the whole work =$\frac{\text{Total work}}{\text{Total efficiency}}$
$=\frac{174}{11}$ days
Hence, the correct answer is $\frac{174}{11}$ days.

SSC CGL Complete Guide

Candidates can download this ebook to know all about SSC CGL.

Download EBook

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books