13 Views

Question : A is 40% more efficient than B. How much time will both, working together, take to finish the work, which B alone can finish in 36 days?

Option 1: $18$ days

Option 2: $9 \frac{1}{3}$ days

Option 3: $15$ days

Option 4: $11 \frac{2}{3}$ days


Team Careers360 17th Jan, 2024
Answer (1)
Team Careers360 18th Jan, 2024

Correct Answer: $15$ days


Solution : Let the efficiency of B be $10a$.
So, efficiency of A = $10a \times 140\%=14a$
So, total work = $10a\times 36=360a$
Now, if they both work then time required = $\frac{360a}{14a + 10a} = \frac{360a}{24a}=\frac{360}{24} = 15$ days
Hence, the correct answer is 15 days.

SSC CGL Complete Guide

Candidates can download this ebook to know all about SSC CGL.

Download EBook

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books