Question : A is 40% more efficient than B. How much time will they take to work together to complete a job which A alone could have done in 31 days?
Option 1: $\frac{217}{12}\ \text{days}$
Option 2: $\frac{515}{32}\ \text{days}$
Option 3: $\frac{215}{12}\ \text{days}$
Option 4: $\frac{517}{32}\ \text{days}$
Latest: SSC CGL preparation tips to crack the exam
Don't Miss: SSC CGL complete guide
New: Unlock 10% OFF on PTE Academic. Use Code: 'C360SPL10'
Correct Answer: $\frac{217}{12}\ \text{days}$
Solution : Given: A is 40% more efficient than B. The time taken by A to complete the task alone is 31 days. Work = Time × Efficiency. Let B's efficiency be 100. Then, $\frac{A}{B} = \frac{140}{100}$ ⇒ $\frac{A}{B} = \frac{7}{5}$ The total work is done by A in 31 days. Let the total work = 31 × 7 = 217 units So, the time taken with A and B working together $=\frac{217}{7+5}=\frac{217}{12}$ days Hence, the correct answer is $\frac{217}{12}\ \text{days}$.
Candidates can download this ebook to know all about SSC CGL.
Answer Key | Eligibility | Application | Selection Process | Preparation Tips | Result | Admit Card
Question : A alone can do $\frac{2}{5}$ of a work in 12 days. B is 25% more efficient than A. C alone can do the same work in 12 days less than B. D is 25% less efficient than C. If they all work together, then the work will be completed in how many days?
Question : A is 20% more efficient than B. How much time will they working together take to complete a job which A alone could have done in 29 days?
Question : Rekha alone can complete a task in 16 days and Bina alone can complete the same task in 12 days. Starting with Rekha, they work on alternate days. The task will be completed in:
Question : If Anju is 30% more efficient than Bittu, then how much time will they take, working together, to complete a job which Anju alone could have done in 23 days?
Question : Anshu, Swati, and Rajni can finish a work in 4 days if they work together. However, Anshu alone will take 9 days to complete the work, and Swati alone will complete the work in 12 days. How many days will Rajni alone take to complete the work?
Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile