45 Views

Question : A is 40% more efficient than B. How much time will they take to work together to complete a job which A alone could have done in 31 days?

Option 1: $\frac{217}{12}\ \text{days}$

Option 2: $\frac{515}{32}\ \text{days}$

Option 3: $\frac{215}{12}\ \text{days}$

Option 4: $\frac{517}{32}\ \text{days}$


Team Careers360 12th Jan, 2024
Answer (1)
Team Careers360 24th Jan, 2024

Correct Answer: $\frac{217}{12}\ \text{days}$


Solution : Given: A is 40% more efficient than B.
The time taken by A to complete the task alone is 31 days.
Work = Time × Efficiency.
Let B's efficiency be 100.
Then, $\frac{A}{B} = \frac{140}{100}$
⇒ $\frac{A}{B} = \frac{7}{5}$
The total work is done by A in 31 days.
Let the total work = 31 × 7 = 217 units
So, the time taken with A and B working together $=\frac{217}{7+5}=\frac{217}{12}$ days
Hence, the correct answer is $\frac{217}{12}\ \text{days}$.

SSC CGL Complete Guide

Candidates can download this ebook to know all about SSC CGL.

Download EBook

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books