4 Views

Question : A work can be completed by 20 men in 50 days. 30 more men join them after 10 days of work. How many days will be saved in the completion of the work?

Option 1: 18 days

Option 2: 20 days

Option 3: 24 days

Option 4: 28 days


Team Careers360 23rd Jan, 2024
Answer (1)
Team Careers360 25th Jan, 2024

Correct Answer: 24 days


Solution : 20 men can finish a work = 50 days
Let the number of days taken after the increment of 30 people be $x$.
According to the question,
Total work = Efficiency × Time = 50 × 20
M1 × D1 = M2 × D2
⇒ 20 × 50 = 20 × 10 + 50 × $x$
⇒ 50 × $x$ = 800
⇒ $x$ = 16
Total time taken = 10 + 16 = 26 days
$\therefore$ Number of days saved = 50 – 26 = 24 days
Hence, the correct answer is 24 days.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
GRE ® Registrations 2024
Apply
Apply for GRE® Test now & save 10% with ApplyShop Gift Card | World's most used Admission Test for Graduate & Professional Schools
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books