Question : Ajay, Vijay, and Sashi can do a piece of work in 20, 40, and 60 days, respectively. In how many days can Ajay do the work if he is assisted by Vijay and Sashi on every fourth day?
Option 1: 15 days
Option 2: $\frac{50}{3}$ days
Option 3: $12$ days
Option 4: $\frac{44}{3}$ days
New: SSC MTS 2024 Application Form OUT; Direct Link
Don't Miss: Month-wise Current Affairs | Upcoming Government Exams
New: Unlock 10% OFF on PTE Academic. Use Code: 'C360SPL10'
Correct Answer: $\frac{50}{3}$ days
Solution : Ajay takes = 20 days Vijay takes = 40 days Sashi takes = 60 days Vijay and Sashi assisted on every fourth day. Total work = LCM(20, 40, 60) = 120 units Efficiency of Ajay = $\frac{120}{20}$ = 6 units/day Efficiency of Vijay = $\frac{120}{40}$ = 3 units/day Efficiency of Sashi = $\frac{120}{60}$ = 2 units/day Ajay's 3 days work = 6 × 3 = 18 units Ajay, Vijay and Sashi one day work = 6 + 3 + 2 = 11 units $\therefore$ Work done in 4 days = 18 + 11 = 29 $\therefore$ Work done in 16 days = 29 × 4 = 116 units Remaining work = 120 – 116 = 4 units Ajay done 4 units work in $\frac{4}{6}$ or $\frac{2}{3}$ days. Total days taken by Ajay to complete the work if he is assisted by Vijay and Sashi on every fourth day = 16 + $\frac{2}{3}$ = $\frac{50}{3}$ days Hence, the correct answer is $\frac{50}{3}$ days.
Application | Cutoff | Selection Process | Preparation Tips | Eligibility | Exam Pattern | Admit Card
Question : A, B, and C can do a piece of work in 10, 20, and 30 days, respectively. In how many days can A do the work if he is assisted by B and C on every third day?
Question : A and B together can do a piece of work in 24 days. A alone can do this work in 40 days. In how many days can B alone do this work?
Question : A alone can do a piece of work in 10 days. B alone can do the same work in 12 days. They work on alternate days starting with A. In how many days will they complete $\frac{3}{4}$th of the total work?
Question : X and Y together can do a work in 10 days. Y and Z together can do the same work in 15 days. Z and X together can do the same work in 12 days. In how many days can Z alone do the same work?
Question : $\mathrm{N}_1$ alone can do 20% of a piece of work in 6 days, $\mathrm{N}_2$ alone can do 20% of the same work in 4 days, and $\mathrm{N}_3$ alone can do 50% of the same work in 12 days. In how many days can they complete the work, if all of them work together?
Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile