Question : A's efficiency is twice that of B's. A can work only for 8 hours a day while B can work for 12 hours a day. If A can finish a task in 12 days, in how many days can B finish the same task?

Option 1: 8

Option 2: 10

Option 3: 16

Option 4: 12


Team Careers360 17th Jan, 2024
Answer (1)
Team Careers360 24th Jan, 2024

Correct Answer: 16


Solution : The ratio of the rates of work of A : B = 2 : 1
Work = efficiency × time
Let the time B takes be $x$ days
A's work = 2 × 12 × 8
B's work = 1 × 12 × $x$
The total work is the same.
Thus, A's work = B's work
⇒ 2 × 12 × 8 = 1 × 12 × $x$
⇒ $x$ = 16 days
Hence, the correct answer is 16.

SSC CGL Complete Guide

Candidates can download this ebook to know all about SSC CGL.

Download EBook

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
GRE ® Registrations 2024
Apply
Apply for GRE® Test now & save 10% with ApplyShop Gift Card | World's most used Admission Test for Graduate & Professional Schools
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books