Question : P, Q, and R can complete a work alone in 12,15, and 20 days respectively. They started the work together. P left the work 8 days before the work was completed and Q left the work 5 days after P had left. R completed the remaining work alone. How many days will be required to complete the whole work?
Option 1: $\frac{32}{3}$ days
Option 2: $10$ days
Option 3: $\frac{28}{3}$ days
Option 4: $\frac{25}{3}$ days
New: SSC CHSL tier 1 answer key 2024 out | SSC CHSL 2024 Notification PDF
Recommended: How to crack SSC CHSL | SSC CHSL exam guide
Don't Miss: Month-wise Current Affairs | Upcoming government exams
New: Unlock 10% OFF on PTE Academic. Use Code: 'C360SPL10'
Correct Answer: $\frac{28}{3}$ days
Solution : Given that P can complete the work in 12 days, Q can complete the work in 15 days, and R can complete the work in 20 days. P left the work 8 days before it was completed, Q left the work 5 days after P had left, and R completed the remaining work alone. Total work = LCM$(12, 15, 20) = 60$ Efficiency of P = $\frac{60}{12} = 5$ Efficiency of Q = $\frac{60}{15} = 4$ Efficiency of R = $\frac{60}{20} = 3$ Let the total work be done in $t$ days. According to the question, ⇒ $5(t - 8) + 4(t - 3) + 3t = 60$ ⇒ $5t - 40 + 4t - 12 + 3t = 60$ ⇒ $12t = 112$ ⇒ $t = \frac{112}{12} = \frac{28}{3}$ days Hence, the correct answer is $\frac{28}{3}$ days.
Candidates can download this e-book to give a boost to thier preparation.
Result | Eligibility | Application | Admit Card | Answer Key | Preparation Tips | Cutoff
Question : A, B, and C can complete a work in 10, 12 and 15 days respectively. A left the work 5 days before the work was completed and B left 2 days after A had left. Number of days required to complete the whole work is:
Question : Rahul alone can complete a work in 10 days and Sonu alone can complete the same work in 15 days. If they work together for 4 days, then what part of total work is left?
Question : A can finish a work in 25 days, and B can do the same work in 15 days. B worked for 10 days and left the job. A alone can finish the remaining work in how many days?
Question : A and B together can complete a piece of work in 15 days and B alone can complete it in 21 days. In how many days can A complete it alone?
Question : A and B together can complete a work in 20 days. B and C together can complete the same work in 15 days. If A, B, and C all work together, then the same work gets completed in 10 days. How many days will A and C together take to complete the same work?
Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile