26 Views

Question : P, Q, and R can complete a work alone in 12,15, and 20 days respectively. They started the work together. P left the work 8 days before the work was completed and Q left the work 5 days after P had left. R completed the remaining work alone. How many days will be required to complete the whole work?

Option 1: $\frac{32}{3}$ days

Option 2: $10$ days

Option 3: $\frac{28}{3}$ days

Option 4: $\frac{25}{3}$ days


Team Careers360 18th Jan, 2024
Answer (1)
Team Careers360 23rd Jan, 2024

Correct Answer: $\frac{28}{3}$ days


Solution : Given that P can complete the work in 12 days, Q can complete the work in 15 days, and R can complete the work in 20 days.
P left the work 8 days before it was completed, Q left the work 5 days after P had left, and R completed the remaining work alone.
Total work = LCM$(12, 15, 20) = 60$
Efficiency of P = $\frac{60}{12} = 5$
Efficiency of Q = $\frac{60}{15} = 4$
Efficiency of R = $\frac{60}{20} = 3$
Let the total work be done in $t$ days.
According to the question,
⇒ $5(t - 8) + 4(t - 3) + 3t = 60$
⇒ $5t - 40 + 4t - 12 + 3t = 60$
⇒ $12t = 112$
⇒ $t = \frac{112}{12} = \frac{28}{3}$ days
Hence, the correct answer is $\frac{28}{3}$ days.

How to crack SSC CHSL

Candidates can download this e-book to give a boost to thier preparation.

Download Now

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books