22 Views

Question : P, Q, and R can complete a work alone in 12,15, and 20 days respectively. They started the work together. P left the work 8 days before the work was completed and Q left the work 5 days after P had left. R completed the remaining work alone. How many days will be required to complete the whole work?

Option 1: $\frac{32}{3}$ days

Option 2: $10$ days

Option 3: $\frac{28}{3}$ days

Option 4: $\frac{25}{3}$ days


Team Careers360 18th Jan, 2024
Answer (1)
Team Careers360 23rd Jan, 2024

Correct Answer: $\frac{28}{3}$ days


Solution : Given that P can complete the work in 12 days, Q can complete the work in 15 days, and R can complete the work in 20 days.
P left the work 8 days before it was completed, Q left the work 5 days after P had left, and R completed the remaining work alone.
Total work = LCM$(12, 15, 20) = 60$
Efficiency of P = $\frac{60}{12} = 5$
Efficiency of Q = $\frac{60}{15} = 4$
Efficiency of R = $\frac{60}{20} = 3$
Let the total work be done in $t$ days.
According to the question,
⇒ $5(t - 8) + 4(t - 3) + 3t = 60$
⇒ $5t - 40 + 4t - 12 + 3t = 60$
⇒ $12t = 112$
⇒ $t = \frac{112}{12} = \frac{28}{3}$ days
Hence, the correct answer is $\frac{28}{3}$ days.

How to crack SSC CHSL

Candidates can download this e-book to give a boost to thier preparation.

Download Now

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
GRE ® Registrations 2024
Apply
Apply for GRE® Test now & save 10% with ApplyShop Gift Card | World's most used Admission Test for Graduate & Professional Schools
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books