91 Views

Question : Sara can finish a work in 18 days and Tara can complete the same work in 15 days. Tara worked for 10 days and left the job. In how many days can Sara finish the remaining work alone?

Option 1: 6

Option 2: 7

Option 3: 8

Option 4: 5


Team Careers360 16th Jan, 2024
Answer (1)
Team Careers360 22nd Jan, 2024

Correct Answer: 6


Solution : Given: Sara can finish a work in 18 days and Tara can complete the same work in 15 days. Tara worked for 10 days and left the job.
Sara in 1 day can do $\frac{1}{18}$ part of the work.
Tara in 1 day can do $\frac{1}{15}$ part of the work.
So, work done by Tara in 10 days $=\frac{10}{15}=\frac{2}{3}$ part of the work.
Remaining work $= (1–\frac{2}{3})=\frac{1}{3}$ part.
Therefore, Sara can do the remaining work in $(18×\frac{1}{3})=6$ days.
Hence, the correct answer is 6.

SSC CGL Complete Guide

Candidates can download this ebook to know all about SSC CGL.

Download EBook

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books