Question : The daily wages of A and B, respectively, are Rs. 3.50 and Rs. 2.50. When A finishes a certain work, he gets a total wage of Rs. 63. When B does the same work, he gets a total wage of Rs. 75. If both of them do it together, what is the cost of the work?
Option 1: Rs. 67.50
Option 2: Rs. 27.50
Option 3: Rs. 60.50
Option 4: Rs. 70.50
Latest: SSC CGL Tier 1 Result 2024 Out | SSC CGL preparation tips to crack the exam
Don't Miss: SSC CGL Tier 1 Scorecard 2024 Released | SSC CGL complete guide
Suggested: Month-wise Current Affairs | Upcoming Government Exams
Correct Answer: Rs. 67.50
Solution : The daily wages of A and B are Rs. 3.50 and Rs. 2.50, respectively. A gets a total wage of Rs. 63. So, time taken by A = $\frac{63}{3.5}$ = 18 days B gets a total wage of Rs. 75. So, time taken by B = $\frac{75}{2.5}$ = 30 days (A + B)’s 1 day’s work = $\frac{1}{18}+\frac{1}{30}=\frac{4}{45}$ ⇒ Required time = $\frac{45}{4}$ days So, the total wages = $\frac{45}{4}×(3.5+2.5)$ = $\frac{45}{4}×6$ = Rs. 67.50 Hence, the correct answer is Rs. 67.50.
Candidates can download this ebook to know all about SSC CGL.
Result | Eligibility | Application | Selection Process | Preparation Tips | Admit Card | Answer Key
Question : A and B worked together and received a total of Rs. 18,000 for 15 days. A's efficiency in the work was 5 times that of B's. The daily wage of A (in Rs.) was:
Question : A sum of Rs. 730 was divided among A, B and C in such a way that if A gets Rs. 3, then B gets Rs. 4. And if B gets Rs. 3.50, then C gets Rs. 3. The share of B exceeds that of C by:
Question : A company employed 700 men and 300 women and the average wage was Rs.450 per day. If a man got Rs.50 more than a woman, then the daily wage of the woman is:
Question : A, B, and C can work together for Rs. 550. A and B together are to do $\frac{7}{11}$ of the work. The share of C should be:
Question : S, T, and U can complete a work in 40, 48, and 60 days, respectively. They received Rs. 10,800 to complete the work. They began the work together, but T left 2 days before the completion of the work and U left 5 days before the completion of the work. S has completed the