6 Views

Question : Working 15 hours a day, Vaibhav can complete a piece of work in 35 days. How many hours a day should he work to finish the work in 25 days?

Option 1: 21 hours

Option 2: 20 hours

Option 3: 18 hours

Option 4: 17 hours


Team Careers360 2nd Jan, 2024
Answer (1)
Team Careers360 17th Jan, 2024

Correct Answer: 21 hours


Solution : Total time taken = 15 × 35 = 525 hours
$\therefore$ Time needed daily to complete the work in 25 days = $\frac{525}{25}$ = 21
Hence, the correct answer is 21 hours.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books