132 Views

Question : X and Y can complete a work in 9 days and 36 days, respectively. X begins to do the work and they work alternately one at a time for one day each. The whole work will be completed in:

Option 1: $12\frac{1}{2}$ days

Option 2: $14\frac{1}{4}$ days

Option 3: $13\frac{1}{3}$ days

Option 4: $15\frac{1}{5}$ days


Team Careers360 7th Jan, 2024
Answer (1)
Team Careers360 25th Jan, 2024

Correct Answer: $14\frac{1}{4}$ days


Solution : Let total Work = LCM (9, 36) = 36 units
The rate of work done by X in 1 day = 4 units
The rate of work done by Y in 1 day = 1 unit
The combined work done by both X and Y works alternately for one day each = 5 units
So, 35 units of work be done in 14 days. Remaining 1 unit work be done by X in $\frac{1}{4}$ days
So, total time taken = $14\frac{1}{4}$ days
Hence, the correct answer is $14\frac{1}{4}$ days.

SSC CGL Complete Guide

Candidates can download this ebook to know all about SSC CGL.

Download EBook

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books