Question : X and Y can complete a work in 9 days and 36 days, respectively. X begins to do the work and they work alternately one at a time for one day each. The whole work will be completed in:
Option 1: $12\frac{1}{2}$ days
Option 2: $14\frac{1}{4}$ days
Option 3: $13\frac{1}{3}$ days
Option 4: $15\frac{1}{5}$ days
Latest: SSC CGL preparation tips to crack the exam
Don't Miss: SSC CGL complete guide
New: Unlock 10% OFF on PTE Academic. Use Code: 'C360SPL10'
Correct Answer: $14\frac{1}{4}$ days
Solution : Let total Work = LCM (9, 36) = 36 units The rate of work done by X in 1 day = 4 units The rate of work done by Y in 1 day = 1 unit The combined work done by both X and Y works alternately for one day each = 5 units So, 35 units of work be done in 14 days. Remaining 1 unit work be done by X in $\frac{1}{4}$ days So, total time taken = $14\frac{1}{4}$ days Hence, the correct answer is $14\frac{1}{4}$ days.
Candidates can download this ebook to know all about SSC CGL.
Answer Key | Eligibility | Application | Selection Process | Preparation Tips | Result | Admit Card
Question : A and B can complete a work in 10 and 16 days respectively. A begins to do the work and they work alternatively one at a time for one day each. The whole work will be completed in:
Question : A, B, and C can do a piece of work in 30, 20, and 10 days respectively. A is assisted by B on one day and by C on the next day, alternately. How long would the work take to finish?
Question : A and B can complete a piece of work in 13 and 17 days respectively. A begins to do the work, and they work alternatively one at a time for one day each. The whole work will be completed in:
Question : If $(x-\frac{1}{3})^2+(y-4)^2=0$, then what is the value of $\frac{y+x}{y-x}$?
Question : If $x=a^{\frac{1}{2}}+a^{-\frac{1}{2}}$, $y=a^{\frac{1}{2}}- a^{-\frac{1}{2}}$, then the value of $(x^{4}-x^{2}y^{2}-1)+(y^{4}-x^{2}y^{2}+1)$ is:
Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile