100 Views

Question : X and Y can complete a work in 9 days and 36 days, respectively. X begins to do the work and they work alternately one at a time for one day each. The whole work will be completed in:

Option 1: $12\frac{1}{2}$ days

Option 2: $14\frac{1}{4}$ days

Option 3: $13\frac{1}{3}$ days

Option 4: $15\frac{1}{5}$ days


Team Careers360 7th Jan, 2024
Answer (1)
Team Careers360 25th Jan, 2024

Correct Answer: $14\frac{1}{4}$ days


Solution : Let total Work = LCM (9, 36) = 36 units
The rate of work done by X in 1 day = 4 units
The rate of work done by Y in 1 day = 1 unit
The combined work done by both X and Y works alternately for one day each = 5 units
So, 35 units of work be done in 14 days. Remaining 1 unit work be done by X in $\frac{1}{4}$ days
So, total time taken = $14\frac{1}{4}$ days
Hence, the correct answer is $14\frac{1}{4}$ days.

SSC CGL Complete Guide

Candidates can download this ebook to know all about SSC CGL.

Download EBook

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
GRE ® Registrations 2024
Apply
Apply for GRE® Test now & save 10% with ApplyShop Gift Card | World's most used Admission Test for Graduate & Professional Schools
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books