125 Views

Question : A and B can complete a work together in 48 days. A is 4 times as work-efficient as B. In how many days can B alone complete the work?

Option 1: 220 days

Option 2: 320 days

Option 3: 240 days

Option 4: 120 days


Team Careers360 17th Jan, 2024
Answer (1)
Team Careers360 18th Jan, 2024

Correct Answer: 240 days


Solution : Efficiency A : B = 4 : 1
If B does 1 unit of work A will do 4 units of work.
So in a day, they will complete 5 units of work together.
We know that total work done = Number of days × Efficiency
Total work done = (48 days × 5 units/day) = 240 units
So, B can complete the whole work alone in $\frac{240}{1}=240$ days.
Hence, the correct answer is 240 days.

SSC CGL Complete Guide

Candidates can download this ebook to know all about SSC CGL.

Download EBook

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books