Question : A is 50% more efficient than B. B finished the same work in 20 days. If A and B worked together, then how much time would they take to finish the same work?

Option 1: 10 days

Option 2: 7 days

Option 3: 8 days

Option 4: 9 days


Team Careers360 9th Jan, 2024
Answer (1)
Team Careers360 18th Jan, 2024

Correct Answer: 8 days


Solution : Let the efficiency of B be 100.
So, the efficiency of A = 100 + 50 =150
The efficiency ratio of A and B = 150 : 100 = 3 : 2
Total efficiency = 3 + 2 = 5 units
The time taken by B to finish the work is 20 days.
So, Total work = Efficiency of B × Time taken by B
⇒ Total work = 2 × 20 = 40 units
Time taken by (A + B) to complete the work
= $\frac{\text{Total work}}{\text{Total efficiency}}$
= $\frac{40}{5}$
= $8$ days
A and B together will finish the work in 8 days.
Hence, the correct answer is 8 days.

SSC CGL Complete Guide

Candidates can download this ebook to know all about SSC CGL.

Download EBook

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
GRE ® Registrations 2024
Apply
Apply for GRE® Test now & save 10% with ApplyShop Gift Card | World's most used Admission Test for Graduate & Professional Schools
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books